2012-11-21 - 5420 - Service Request - SO delivery proposal dates #ProductionBreakFix #MMPPSupport #Calendar
5420 - Service Request - SO delivery proposal dates
Summary Description
SO delivery proposal dates.
Admin Info
Purpose
|
SO delivery proposal dates
|
Requested by
|
Will Cartwright
|
Issue Date
|
11-21-2012
|
Resolved by
|
Adithya
|
Resolved Date
|
11-23-2012
|
Document Status
|
Complete
|
Detailed Description
(Include Screen Shots if required )
Sales Order delivery date proposed later even though stock exists.
Analysis and Recommendations
(Include Screen Shots if required)
Though Stock is existing in sales order delivery dates are pushed to future, because of the wrong calendar.
Resolution
Calenders assigned for routes are wrong.
Release Information
2012-11-26 - 5422 - Break Fix - Wrong Factory Calendar